Project History

Sept. – Nov. 1998

Liturgical formation process

May/June 1999

Town Hall Meetings for master planning

September 1999

Interviewed professional fundraisers

December 1999

Preliminary Review Procedure (PRP) application filed with the City of Fremont

February 2000

City provided comments on PRP application

Feb. to June 2000

City input and meetings with neighbors. Master Plan was updated, we began 2-acre land acquisition process with Dominican Sisters

Summer 2000

Preliminary assessment of first phase of project cost as $10,200,000

September 2000

Capital campaign began with target goal of $4,000,000 in pledges. The 4 million target was simply the calculation of annual offertory times a factor. Due to the size of the parish, the per capita income of the majority of families registered at St. Joseph, and the large amount of “loose change” donors it was also felt that a target of 5 million was achievable. Raising pledges of half the cost would permit construction to begin.

November 2000

Monsignor Simas and Coordinating Committee members appeared before Planning Commission on Mission San Jose Planned District (MSJPD) to voice concerns

March/April 2001

Final concerns worked out with City staff members, City Council adopts MSJPD guidelines

May 2001

Consultants were retained to prepare parcel map including civil engineer, soil engineer and biological assessment

August 2001

Application for parcel map filed with City including maps and reports from all consultants

October 2001

Planning Commission approved parcel map with concerns about creek

May 16 & 17, 2002

Town Hall Meeting

May 2002

City staff finalized review of map for recordation with County

June 15, 2002

Design Church committee tours area churches to gather ideas.

June 26, 2002

Design Committee Meeting - Tour Debrief and Consensus Notes

July 22, 2002

Design Church committee meeting - Schematic Design: Presentation (Zip) & Minutes (PDF)

August 26, 2002

Design Church committee meeting - Schematic Design: Minutes (PDF)

September 16, 2002

Design Church committee meeting - Schematic Design: Minutes (PDF)

October 28, 2002

Design Church committee meeting - Schematic Design: Minutes (PDF)

November 6, 2002

Town Hall Meeting

January 20, 2003

Design Church committee meeting - Design Development

April 7, 2003

Design Church committee meeting - Design Development: Minutes (PDF)

January 2006

“Story Poles” installed at building site.

February 2, 2006

City of Fremont Historical Architectural Review Board (HARB) meeting - Unanimous 7 to 0 vote

February 23, 2006

City of Fremont planning commission - Unanimous 5 to 0 vote

March 28, 2006

City council meeting - The City Council unanimously voted 5-0 in favor of our new church!!

March 30, 2006

Building and Design Committee Meeting: Shrines & Images and Art & Environment - Minutes

April 1, 2006

Advisory meeting

May 9 & 31 and June 14, 2006

Design Church committee meeting - Meeting Minutes: [1] [2] [3] [4] (PDF)

June 23, 2006

New Church Gala Groundbreaking Festivity!

August 16, 2006

Building and Design Committee Meeting: Introduction of Brother Joe’s work and discussion about interior materials and appearance of ducts. Some of this presentation was used.

September 8, 2006

Capital Campaign II Kickoff - Building a People of Faith

September 19, 2006

Building and Design Committee Meeting: Discussion about the font design, glass, stations of the cross, and other fixtures.

November 2, 2006

City of Fremont Historical Architectural Review Board (HARB) voted unanimously to approve the St. Joseph Rectory Relocation. Details about the relocation are here.

November 16, 2006

Building and Design Committee  Meeting: In this meeting we had two Presentations about refinements to the interior space architecture as well as the Liturgical furnishings.

February 1, 2007

Building and Design Committee  Meeting: In this meeting we had two Presentations about further refinements to the exterior and interior architecture as well as the Tabernacle and St. Joseph statue.

March 14, 2007

Building and Design Committee  Meeting: In this meeting we had two Presentations about further refinements to the interior architecture as well as the Sanctuary, Lighting, and Liturgical furnishings.

April 18, 2007

Building and Design Committee  Meeting: In this meeting we had two Presentations about interior & exterior architecture, Sanctuary, Ambo, Stations of the Cross, and Presider’s Chair.

April 19, 2007

Today we received our GRADING and RECTORY Relocation permit OK from the City of Fremont! - Hallelujah!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!! -- Many thanks go out for the persistence and hard work by TBI construction and the Steinberg team to finally get to this point! -- This is  the first thing that must happen in order to make room for the construction of the new church on the old rectory location!

April 23, 2007

Equipment arrives - Construction begins !!! - Expect to see lots of activity!!!!!!!!

June 18, 2007

Building and Design Committee  Meeting: In this meeting we had three Presentations about the interior architecture, exterior landscape and liturgical furnishings, in particular the Stations of the Cross.

July 25, 2007

The stain glass restoration is making significant progress. Click here for more detailed photos.

October 26, 2007

Rectory move is complete and ready for occupancy. Finishing touches have been made after the building move. Click here for more detailed photos.

 

WHAT’S NEXT? Click here to see the project schedule.